Question: You are a project manager working on a project to build a new car . Due to a change in regulations imposed by the federal
You are a project manager working on a project to build a new car . Due to a change in regulations imposed by the federal government , the materials currently being used pose a safety risk , and the project sponsor has asked you to change the materials used to construct the car How should you handle this situation ? A Adhere to the organization's change control process . B Refuse to make the change . Immediately implement the change and submit it to the change control board afterward D Review the risk management plan