Question: You are administering a commercial contract for aircraft engine component spares. The contractor missed the delivery date and failed to respond to a show cause
You are administering a commercial contract for aircraft engine component spares. The contractor missed the delivery date and failed to respond to a show cause notice. The contracting officer then issued a termination for cause notice. The engine spares are still needed. Which choice below represents the proper order of actions to take?
-Demand compensatory payment from the terminated contractor before re-procuring,re-procure the remaining requirement, document the file explaining the action taken.
-Discuss the matter with your customer, re-procure the remaining requirement, require payment of excess re-procurement costs from the terminated contractor, document the file explaining the actions taken.
-Document the file explaining the actins taken, re-procure the remaining requirement, discuss the matter with legal counsel.
-Amend the termination notice to reflect the amount owed by the contractor, document the file explaining the actions taken, re-procure the remaining requirement, discuss the matter with legal counsel.