You are analyzing a project and have prepared the following data: YearCash flow 0- $192,700 1 $53,200
Fantastic news! We've Found the answer you've been seeking!
Question:
You are analyzing a project and have prepared the following data:
YearCash flow
0-
$192,700
1
$53,200
2
$77,600
3
$51,000
4
$26,00
Required payback period
3.5 years
Required AAR
8.25 percent
Required return
10.50 percent
Based on the profitability index of _____ for this project, you should _____ the project.
- 1.08; reject
- 0.87; accept
- 1.02; accept
- 0.87; reject
- 1.02; reject