Question: You are analyzing a proposed project and have compiled the following inform Year 0 1 2 3 Cash Flow -$158,000 34,500 78,500 92,000 Required payback
You are analyzing a proposed project and have compiled the following inform Year 0 1 2 3 Cash Flow -$158,000 34,500 78,500 92,000 Required payback period 2.5 years 12 percent Required return Should the proposed project be accepted based on its payback period? Why or why not? OA) yes; PB = 2.49 years OB) yes; PB = 2.51 years Oc) no; PB = 2.49 years D) no; PB = 2.51 years