Question: You are analyzing the following two mutually exclusive projects and have developed the following information. Please calculate the IRRs for the two projects and the
You are analyzing the following two mutually exclusive projects and have developed the following information. Please calculate the IRRs for the two projects and the crossover rate. (6 points) Which project should you accept if the cost of capital is 5%, and which project should you accept if the cost of capital is 10%? (4 points)
year project A project B
0 -1100 -900
1 400 700
2 500 100
3 100 100
4 400 200
IRR A: ___________ IRR B: ___________ Crossover Rate: ____________ If WACC=5%, accept _______ If WACC=10%, accept _______