Question: You are assigned your first project and if things go well you should get promoted. The CEO is aware of this project, so you have

You are assigned your first project and if things go well you should get promoted. The CEO is aware of this project, so you have a chance for high visibility. You want to do a good job! Your first task is to de interviewing project activity managers and the firm's friendly, yet boring, accountants to get "good estimates" of project activity times and costs. For one of the activities, the normal time is three weeks, th cost is $7,190, and the crash cost is $16,475. What is the crash cost per week? Round your answer to the nearest dollar.
$ per week
 You are assigned your first project and if things go well

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!