Question: You are choosing between two projects. The cash flows for the projects are given in the following table ($ million): a. What are the IRRs


You are choosing between two projects. The cash flows for the projects are given in the following table ($ million): a. What are the IRRs of the two projects? b. If your discount rate is 5.1%, what are the NPVs of the two projects? c. Why do IRR and NPV rank the two projects differently? X i Data Table (Click on the following icon in order to copy its contents into a spreadsheet.) Project A B Year 0 - $51 - $101 Year 1 $26 $21 Year 2 $18 $42 Year 3 $22 $50 Year 4 $14 $61 Print Done