You are comparing actual results to the plan and making calculations to determine the project's rate of
Fantastic news! We've Found the answer you've been seeking!
Question:
You are comparing actual results to the plan and making calculations to determine the project's rate of performance. What are you doing? option A Cost aggregation option B Reserve analysis option C Controlling costs option D Estimating costs