Question: You are comparing two projects. Using the data below, calculate the CV, SV, SPI, and CPI. Second, use the values to provide the status of

You are comparing two projects. Using the data below, calculate the CV, SV, SPI, and CPI. Second, use the values to provide the status of each project. All values are in dollars.

Project AProject B
EV450550
PV465575
AC425650

Step by Step Solution

3.40 Rating (153 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Formula EVAC Project A 450425 25 Project B 550650100 1 CV Project A is under budget ... View full answer