Question: You are considering a project that has been assigned a discount rate of 14.3 percent. If you start the project today, you will incur an
You are considering a project that has been assigned a discount rate of 14.3 percent. If you start the project today, you will incur an initial cost of $11,400 and will receive cash inflows of $6,800 a year for two years. If you wait one year to start the project, the initial cost will rise to $12,100 and the cash flows will increase to $7,200 a year for two years. What is the value of the option to wait?
Multiple Choice
$28.51
$9.46
$7.63
$33.02
$30.49
Step by Step Solution