Question: You are considering a project that has been assigned a discount rate of 11%. If you start the project today, you will incur an initial

You are considering a project that has been assigned a discount rate of 11%. If you start the project today, you will incur an initial cost of $470 and will receive cash inflows of $353 a year for three years. If you wait one year to start the project, the initial cost will rise to $517 and the cash flows will increase to $395 a year for three years.

What is the value of the option to wait?(Round answer to 2 decimal places, round intermediate calculations to 5 decimal places)

Value of the Option to Wait?