Question: You are considering a project that has been assigned a discount rate of 12 percent. If you start the project today, you will incur an
You are considering a project that has been assigned a discount rate of 12 percent. If you start the project today, you will incur an initial cost of $280 and will receive cash inflows of $350 a year for three years. If you wait one year to start the project, the initial cost will rise to $420 and the cash flows will increase to $385 a year for three years. What is the value of the option to wait?