Question: You are considering a project which has been assigned a discount rate of 6 percent. If you start the project today, you will incur an
You are considering a project which has been assigned a discount rate of 6 percent. If you start the project today, you will incur an initial cost of $4,200 and will receive cash inflows of $3,000 a year for 2 years. If you wait one year to start the project, the initial cost will rise to $4,420 and the cash flows will increase to $3,357 a year for 2 years. What is the value of the option to wait?
$434.52
$3,371.21
$611.62
$336.33
$508.12
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts