Question: You are considering a project which has been assigned a discount rate of 9 percent. If you start the project today, you will incur an
You are considering a project which has been assigned a discount rate of 9 percent. If you start the project today, you will incur an initial cost of $4,500 and will receive cash inflows of $3,300 a year for 2 years. If you wait one year to start the project, the initial cost will rise to $4,720 and the cash flows will increase to $3,657 a year for 2 years. What is the value of the option to wait? (Do not round intermediate calculations.)
$628.93
$408.00
$515.76
$3,284.69
$266.56