Question: You are considering constructing a new plant in a remote wilderness area to process the ore from a planned mining operation. You anticipate that the
You are considering constructing a new plant in a remote wilderness area to process the ore from a planned mining operation. You anticipate that the plant will take a year to build and cost
$ 96 million upfront. Once built, it will generate cash flows of $ 12 million per year starting two years from today. In 21 years, after its 20th year of operation, the mine will run out of ore and you expect to pay $ 144 million to shut the plant down and restore the area to its pristine state. Using a cost of capital of 12 %
:a. What is the NPV of the project?
b. Is using the IRR rule reliable for this project? Explain.
c. What are the IRRs of this project?
Question content area bottom
Part 1
a. What is the NPV of the project?
The NPV of the project is
$enter your response here
million. (Round to one decimal place.)
Part 2
b. Is using the IRR rule reliable for this project? Explain.(Select the best choice below.)
A.
Yes, the IRR rule is reliable, because the project has a negative net present value.
B.
Yes, the IRR rule is reliable, because the project has a negative cash flow that comes after the positive ones.
C.
No, the IRR rule is not reliable, because the project has a negative net present value.
D.
No, the IRR rule is not reliable, because the project has a negative cash flow that comes after the positive ones.
Part 3
c. What are the IRRs of this project?
The IRRs of this project in ASCENDING order are
enter your response here
%
and
enter your response here
%.
(Round to two decimal places.)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts