Question: You are considering the following two mutually exclusive projects. The required rate of return is 12 percent for both projects. Which project should you accept

You are considering the following two mutually exclusive projects. The required rate of return is 12 percent for both projects. Which project should you accept and why? a. You are indifferent; because the sums of the cash flows for both projects are identical b. Project A; because its NPV is higher than the NPV for project B c. Project B; because its NPV is higher than the NPV for project A d. Project A; because mutually exclusive projects should be accepted in the order of arrival e. Project B; because it has larger cash flows towards the end of the project