Question: You are considering three independent projects: project A, project B, and project C. Given the free cash flow information in the popup window, calculate the
You are considering three independent projects: project A, project B, and project C. Given the free cash flow information in the popup window, calculate the payback period for each. If you require a 3-year payback before an investment can be accepted, which project(s) would be accepted?
Initial Outlay -950 -9,500 -5,500
Inflow year 1 500 6,000 1,000
Inflow year 2 300 2,000 1,000
Inflow year 3 100 2,000 3,000
Inflow year 4 300 2,000 3,000
Inflow year 5 400 2,000 3,000
What is the payback period of project A?
What is the payback period of project B?
What is the payback period of project C?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts