You are considering two independent projects, Project A and Project B.The initial cash outlay associated with Project
Fantastic news! We've Found the answer you've been seeking!
Question:
You are considering two independent projects, Project A and Project B.The initial cash outlay associated with Project A is $50,000 and the initial cash outlay associated with Project B is $70,000.The discount rate on both projects is 12 percent.The expected annual cash flows from each project are as follows:
Year
Project A
Project B
0
$(50,000)
%(70,000)
1
12,000
13,000
2
12,000
13,000
3
12,000
13,000
4
12,000
13,000
5
12,000
13,000
6
12,000
13,000
Calculate the NPV, PI, and IRR for each project and indicate if the project should be accepted or not.
Discuss the differences between the three values you found - compare and contrast these three methods.
Posted Date: