Question: You are considering two mutually exclusive projects. Project A has cash flows of-$72,000, $21,400, $22,900, and $56,300 for Years 0 to 3, respectively. Project B
You are considering two mutually exclusive projects. Project A has cash flows of-$72,000, $21,400, $22,900, and $56,300 for Years 0 to 3, respectively. Project B has cash flows of-$81,000, $20,100, $22,200, and $74,800 for Years 0 to 3, respectively. Both projects have a required 2.5-year payback period. Should you accept or reject these projects based on payback analysis? O A Accept Project A and reject Project B O B Reject Project A and accept Project B OCAccept both Projects A and B O D Reject both Projects A and B E You cannot apply the payback method to these projects