Question: You are considering two mutually exclusive projects with the following cash flows. Which project should you accept if the discount rate is 7 percent? Year
You are considering two mutually exclusive projects with the following cash flows. Which project should you accept if the discount rate is 7 percent?
Year Project A Project B
0 -275,000 -202,000
1 0 113,600
2 0 81,900
3 360,000 47,000
What if the discount rate is 10 percent? Show all work and computations