Question: You are coordinating an event for a client, and the project team includes several key stakeholders from different departments. During the planning phase, the team
You are coordinating an event for a client, and the project team includes several key stakeholders from different departments. During the planning phase, the team begins to express conflicting opinions about the event design and budget. Your team is in the stage of team development.
Performing
Forming
Norming
Storming