Question: You are creating a customer database for the Lehigh Valley IronPigs minor league baseball team. Given the information below, complete the forward and backward pass,
You are creating a customer database for the Lehigh Valley IronPigs minor league baseball team. Given the information below, complete the forward and backward pass, compute activity slack, and identify the critical path.
| ID | Description | Predecessor | Time (days) |
| A | Systems | None | 8 |
| B | Subsystem A design | A | 2 |
| C | Subsystem B design | A | 1 |
| D | Subsystem C design | A | 2 |
| E | Program A | B | 2 |
| F | Program B | C | 10 |
| G | Program C | D | 2 |
| H | Subsystem A test | E | 5 |
| I | Subsystem B test | F | 5 |
| J | Subsystem C test | G | 5 |
| K | Integration | H, I, J | 1 |
| L | Integration test | K | 5 |
Calculate the free slack and total slack for all noncritical activities (Click to select)
How long will this project take?
How sensitive is the network schedule?
What is the total slack on D?
What is the total slack on E?
What is the Free slack on B?
What is the free slack on H?