ID Description Predecessor Time
days
A Systems None
B Subsystem A design A
C Subsystem B design A
D Subsystem C design A
E Program A B
F Program B C
G Program C D
H Subsystem A test E
I Subsystem B test F
J Subsystem C test G
K Integration H I, J
L Integration test K
Calculate the free slack and total slack for all noncritical activities
There is total slack on activities B D E G H and J and free slack on activities H and J
How sensitive is the network schedule?
Not very sensitive There is a single dominant critical path.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock