Question: You are currently working on a new and unique project requirement. The team recognizes the potential for all sorts of things to go wrong, but
You are currently working on a new and unique project requirement. The team recognizes the potential for all sorts of things to go wrong, but currently they don't have the existing data from another group to determine how it will affect the project. Which classification would this fall under?A OBCDUnknown unknownKnown knownKnown unknownUnknown known