Question: You are deciding to choose between three mutually exclusive projects. a. option1: project X will cost $5000 to install and $4200 a year to run
You are deciding to choose between three mutually exclusive projects.
a. option1: project X will cost $5000 to install and $4200 a year to run and will last for three years.
b. option 2: project Y will cost $6000 to install and $3800 a year to run and will last for four years.
c. option 3: project Z will cost $10,000 to install and $500 a year to run and will last forever.
Let the WACC = 0.08
Estimate the NPV of project X.
Estimate the equivalent annuity cost of project X.
Estimate the NPV of project Y.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
