Question: You are developing a performance progress report for your project you are managing. The following time phase budget was developed earlier in the planning stage

You are developing a performance progress report for your project you are managing. The following time phase budget was developed earlier in the planning stage and is being used as the standard against Wister project performance is measured

Work packages w1 w2 w3 w4 w5 w6
A 6 5 9
B 4
C 9 8
Total 6 5 9 4 9 8

you are analyzing the project performance at the end of the week five. Activity C is 80% complete and is the actual cost is 15 what is the scheduled variance of this activity used ?