Question: You are developing a performance progress report for your project you are managing. The following time phase budget was developed earlier in the planning stage
You are developing a performance progress report for your project you are managing. The following time phase budget was developed earlier in the planning stage and is being used as the standard against Wister project performance is measured
| Work packages | w1 | w2 | w3 | w4 | w5 | w6 |
| A | 6 | 5 | 9 | |||
| B | 4 | |||||
| C | 9 | 8 | ||||
| Total | 6 | 5 | 9 | 4 | 9 | 8 |
you are analyzing the project performance at the end of the week five. Activity C is 80% complete and is the actual cost is 15 what is the scheduled variance of this activity used ?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
