Question: You are developing the risk register for your project. Which of the following is not true about the risk register? A It documents potential risk

You are developing the risk register for your project. Which of the following is not true about the risk register?
A It documents potential risk responses
B It is one of three outputs of the Identify Risks Process
C It is the sole output of the Plan Risk Responses process
It documents the results of risk analysis as it is performed.