Question: you are developing the schedule for your project. You have constructed a network diagram representing the activies and their dependencies. you need to calculate the

you are developing the schedule for your project. You have constructed a network diagram representing the activies and their dependencies. you need to calculate the late start and late finish for several activities. which technique would you use?
A) forward pass
B) monte carlo analysis
c) backward pass
d) fast tracking