Question: you are developing the schedule for your project. You have constructed a network diagram representing the activies and their dependencies. you need to calculate the
you are developing the schedule for your project. You have constructed a network diagram representing the activies and their dependencies. you need to calculate the late start and late finish for several activities. which technique would you use?
A forward pass
B monte carlo analysis
c backward pass
d fast tracking