Question: You are finalizing the costs for work packages, activities, and contingency reserves. Because this is a large project, there are many phases and deliverables for
You are finalizing the costs for work packages, activities, and contingency reserves. Because this is a large project, there are many phases and deliverables for this project, and each stage of the project requires a separate approval and sign-off. For this deliverable, you have estimated a total cost of $930,000. The senior management staff has informed you that they will be able to release only $310,000 per quarter, so you should plan activities accordingly. Which tool do you employ to do this?
A) Funding limit reconciliation
B) Cost baseline
C) Project budget
D) Cost aggregation