Question: You are generating the duration estimate for a work package. You have enlisted an SME for advice. The SME gave 8 for the optimistic time,

You are generating the duration estimate for a

You are generating the duration estimate for a work package. You have enlisted an SME for advice. The SME gave 8 for the optimistic time, 19 for most likely time and 53 for pessimistic. Use the Beta probability distribution to determine the expected duration. (no decial is required)