Question: You are given the activity information below and the activity - on - node precedence diagram for a project at your company. 1 6 points
You are given the activity information below and the activityonnode precedence diagram for a project at your company. points error
a Determine the critical path and its duration. What is your initial estimate for project completion time? Show your work on the next page.
b Fill in the table on the next page to determine the earliest start ES time, the earliest finish EF time, the latest start LS time, the latest finish LF time, and the Slack for each project activity. Slack LS ES or LF EF
tableActivity Immediate Predecessors Time daysABCADA BEC DFDGE FHF
Note: This precedence diagram is posted as a separate pdf also.
Problem continues on the next page.
a Fill in the table with each path and show your work by calculating the time for each path in the table to determine the critical longest paths Adddelete rows in the table as needed. You must indicate the critical path and the estimated project completion time below the table.
Path Time
Critical Path
Estimated Project
Completion
b Fill in the ES & EF times in the table below working from Start to Finish. Then, fill in the LS & LF times working backwards from Finish to Start. After determining the ES EF LS & LF times, calculate the Slack time for each activity using both Slack and Slack Note: Both calculations must give you the same answers.
Activity ES EF LS LF Slack
A
B
C
D
E
F
G
H
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock