Question: You are given the following data about project tasks, network, and crash times/costs. Calculate the cost of the project at all time durations until

You are given the following data about project tasks, network, and crash times/costs. Calculate the cost of the project at all time durations until you can no longer crash the project. All times are in days. ID A B C D E F G Normal Time 10 12 11 5 8 9 8 Direct costs Total Direct Costs: A B Crash Maximum Cost Time Cost Slope Crash Time Question 1: Calculate the critical path and the direct costs of the initial network for this project. Enter duration times in the space provided in the network diagram below. Critical Path: Project Duration: $5000 10 $5000 $0 $1200 11 $1300 $100 $3600 9 $4800 $600 $300 4 $600 $300 $1000 6 $2000 $500 $2400 7 $5400 $1500 $700 7 $1000 $300 $14200 C D E 0 1 2 1 2 2 1 F G
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts