You are given the following data regarding the Earned Value results of a project. There are no
Fantastic news! We've Found the answer you've been seeking!
Question:
You are given the following data regarding the Earned Value results of a project. There are no approved change orders for this project.
Calculate ETC, EAC and VAC.
Budget $220,000
Duration 200 days
Status 140 days
EV $180,000
PV $180,000
AC $220,000
BAC ?
Assume that future cost estimates are accurate and do not change.
1) ETC =
2) EAC =
3) VAC =
Related Book For
Introduction to Operations Research
ISBN: 978-1259162985
10th edition
Authors: Frederick S. Hillier, Gerald J. Lieberman
Posted Date: