Question: You are given the following data regarding the Earned Value results of a project. There are no approved change orders for this project. Calculate ETC,
You are given the following data regarding the Earned Value results of a project. There are no approved change orders for this project.
Calculate ETC, EAC and VAC.
Budget $220,000
Duration 200 days
Status 140 days
EV $180,000
PV $180,000
AC $220,000
BAC ?
Assume that future cost estimates are accurate and do not change.
1) ETC =
2) EAC =
3) VAC =
Step by Step Solution
3.47 Rating (150 Votes )
There are 3 Steps involved in it
1 ETC 40000 2 EAC 220000 3 VAC 0 Expla... View full answer