Question: You are given the following data regarding the Earned Value results of a project. There are no approved change orders for this project. Calculate ETC,

You are given the following data regarding the Earned Value results of a project. There are no approved change orders for this project.

Calculate ETC, EAC and VAC.

Budget $220,000

Duration 200 days

Status 140 days

EV $180,000

PV $180,000

AC $220,000

BAC ?

Assume that future cost estimates are accurate and do not change.

1) ETC =

2) EAC =

3) VAC =

Step by Step Solution

3.47 Rating (150 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

1 ETC 40000 2 EAC 220000 3 VAC 0 Expla... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!