Question: You are given the following information. Maximum capacity ( labor hours ) : 5 0 0 hours per week Effective capacity ratio: 9 2 %

You are given the following information.
Maximum capacity (labor hours): 500 hours per week
Effective capacity ratio: 92%
Actual time worked: 325 hours per week over the last two weeks
On-time delivery %: 85 percent of the jobs are being completed on time
Calculate the effective capacity and actual utilization.
Do we need to add more capacity?
You are given the following information.
a. Calculate the effective capacity and actual utilization.
b. Do we need to add more capacity?
Complete this question by entering your answers in the tabs below.
Calculate the effective capacity and actual utilization.
Note: Round your answers to 2 decimal places. Enter "Actual utilization" as a percentage rounded to 2d,
 You are given the following information. Maximum capacity (labor hours): 500

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!