Question: You are given the following information: Time per shift 8.5 hours Number of shifts per day 2 Number of operating days per month 20 Shift

You are given the following information: Time per shift 8.5 hours Number of shifts per day 2 Number of operating days per month 20 Shift transition time 15 minutes per shift Lunch per shift 30 minutes Breaks per shift 2 @ 10 minutes Expected setups 20 minutes per shift Number of orders 23,000 during the month The Takt time for this situation is which of the following? Question 1 options: 1) 25.31 seconds 2) 38.09 seconds 3) 44.35 seconds 4) 46.43 seconds