Question: You are given the following parameters for a project. Activity Duration Immediate Predecessors A 4 -- B 2 -- C 3 A, B D 3
You are given the following parameters for a project.
| Activity |
Duration | Immediate Predecessors |
| A | 4 | -- |
| B | 2 | -- |
| C | 3 | A, B |
| D | 3 | A, B |
| E | 2 | B, C, D |
What is the critical path for the project? Use capital letters and no spaces. i.e. TFR or YG
What is the duration of the project?
How much slack is there in task C?
If the crash costs for each task are A-200, B-150, C-250, D-275, and E-200, you would crash ___ if you were asked to shorten the project by one day. Simply enter the capitalized letter for the task.