Question: You are given the information in the MRP table below. Complete the projected On - hand inventory and planned order releases for weeks 1 to

You are given the information in the MRP table below. Complete the projected On-hand inventory and planned order releases for weeks 1 to 6.
\table[[Part: SKU003| Week #,1,2,3,4,5,6,],[Gross Requirements,80,120,320,220,180,420,],[Schedule Receipts,,300,,,,,],[Projected On-Hand Inventory,240,,,,,,],[Planned Order Releases,,,,,,,],[Q=50;LT=3;SS=20,,,,,,,]]