Question: You are halfway through your project and the earned value is $265. You have spent $200 so this amount is your actual cost. What is
You are halfway through your project and the earned value is $265. You have spent $200 so this amount is your actual cost. What is the cost variance? 1.35 0.75 negative $65 $65