Question: You are in charge of a large software development project. As a part of the project schedule - it was planned to complete two core
You are in charge of a large software development project. As a part of the project schedule it was planned to complete two core components by the end of October. You are now in August and you realize that the project is falling behind schedule. You do a quick review and decide that the schedule can be met by adding additional staff to the activities on the critical path. This is an example of :
a Crashing
b Scope Creep
c Resource Levelling
d Fast Tracking