You are involved in estimating the time it will take to implement a new software package. You
Fantastic news! We've Found the answer you've been seeking!
Question:
You are involved in estimating the time it will take to implement a new software package. You have learned that the most likely time will be days. The pessimistic or longest it should take would be days. If everything goes well the shortest possible time is days. What is the weighed average or expected time using the beta also called threepoint method distribution?