Question: You are involved in estimating the time it will take to implement a new software package. You have learned that the most likely time will

You are involved in estimating the time it will take to implement a new software package. You have learned that the most likely time will be 60 days. The pessimistic or longest it should take would be 72 days. If everything goes well the shortest possible time is 48 days. What is the weighed average or expected time using the beta (also called three-point method) distribution?