Question: You are leading a project that involves installing new operating software for each of the 2,000 computers your company and its employee's use. You know

You are leading a project that involves installing new operating software for each of the 2,000 computers your company and its employee's use. You know from past project files that this was done 5 years ago, when the company had only 1,000 computers to update. You come up with an estimate of time required to complete t his task. Which tool have you used? A. Analogous Estimating B. Reserve Analysis C. Parametric Estimating D. Organizational Process Assets