Question: You are leading a project to develop a new web application. Together with your project team, you reprioritize the product backlog, determine the velocity for

You are leading a project to develop a new web application. Together with your project team, you reprioritize the product backlog, determine the velocity for the past iterations, and adapt your work plans accordingly. Additionally, you facilitate retrospectives every two weeks. Which of the following processes describes the work you are performing?
Group of answer choices
Manage quality
Monitor risks
Develop schedule
Control schedule