Question: You are managing a constructions project. You have completed half the project work. The total planned cost at this stage is $ 1 0 0

You are managing a constructions project. You have completed half the project work. The total planned cost at this stage is $1000. The actual work that has been completed at this stage is worth $1200. You have spent $1500 already on the project. What is the CPI?
a.0.5
b.0.8
c.4
d.1.25