Question: You are managing a Development project. After completion of System Testing. you have performed analysis of defect data along with Defect Prevention ( DP )

You are managing a Development project. After completion of System Testing. you have performed analysis of defect data along with Defect Prevention (DP) Prime. Cause wise defect distribution indicated that more than 75% of the defects are due to causes - "Incorrect coding" and "Incorrect testing": Which technique did you use for the analysis?
Selict the correct optianfy and chich witmt
Structured Brainstorming
5 Whys
Pareto Analysis
Cause and Effect Analysis