Question: You are managing a large, complex project that will take several years to complete. You are currently planning Phase 1 activities in detail and only
You are managing a large, complex project that will take several years to complete. You are currently planning Phase activities in detail and only planning the activities in later Phases at a high level. Which of the following planning approaches does this best describe?
Progressive Elaboration
Rolling Wave Planning
Agile Planning
Adaptive Planning