You are managing a large construction project that is been broken down into subprojects or phases Each of these subprojects is scheduled to take between three and six months to complete. At the end of each sub project, you plan to go through the closing processes and document lessons learned. Which BEST describes what you must do at the beginning of each subproject or phase?
Make sure you don not involve the team, to avoid introducing too much project management overhead
Release all resources from the project and contact sellers to renegotiate all contracts
Identify the stakeholders
Use the Earned Value Technique to decide whether or not to finish the project