Question: You are managing a large software development project with 20 key internal resources, eight contractors, and six team leaders. You have successfully completed the execution
You are managing a large software development project with 20 key internal resources, eight contractors, and six team leaders. You have successfully completed the execution phase of the project. Which of the following should NOT be performed next? Question 15 options: Obtain sponsor sign off verifying the project objectives have been met Perform a final quality check to ensure the software is free of defects Manage the handover of the software to operations Convene a project team meeting to capture lessons learned Celebrate the project success