Question: You are managing a multi-year project whose budget is 500,000 USD. The cost variance is -45,000 USD, the actual cost is 200,000 USD, and the
You are managing a multi-year project whose budget is 500,000 USD. The cost variance is -45,000 USD, the actual cost is 200,000 USD, and the planned value is 140,000 USD. Calculate the schedule variance and comment on the performance.
Step by Step Solution
There are 3 Steps involved in it
To calculate the schedule variance SV we use the formula SV Earned Value EV Planned Value PV Given P... View full answer