Question: You are managing a software engineering project when two team rembers come to you with a conflict. The project's chief developer has detected a significant
You are managing a software engineering project when two team rembers come to you with a conflict. The project's chief developer has detected a significant risk: a subcontractor may tail to deliver on time. According to the experts, there is o 0 , probabitity that the subcontractor would not deliver. It this occurs, your engineers witl be paid an additional $15,250 to rewrite the work, and the company would lase $20,000 in business as a result of the delay. Another team member suggests a way to save money in anothe area to help mitigate the risk. If a preexisting component can be modifled, the project. witl 5ave$4,500 engineering expenses. There is a 65% chance that the team witt be able to capitalize on this opportunity What is the EMV (estimated monetary vatue) of these two items