Question: You are managing a Transportation Management System development project for a major courier service in your country. The project has a big number of stakeholders,

You are managing a Transportation Management System development project for a major courier service in your country. The project has a big number of stakeholders, who have so far struggled with defining the project requirements in a level of detail required for system development. As a result, you have decided to try Agile approaches for system development. With the detailed system requirement not defined, which of the following is one of the major risks on your project? Scope creep Scope control Scope verification Value Added Scope